Showing posts with label Risk Management. Show all posts
Showing posts with label Risk Management. Show all posts
Implement your corporate Risk and Issue Management methodology in Project Online
Project Online (or Project Server) should be configured, not
to say customized, in a way that it supports your business principles and
procedures around Project Management. It should reflect your (probably tailor
made) Project Management methodology. The first thing you generally do is to
configure your way of doing project plans, by creating your own Enterprise
Custom Fields and Lookup Tables that would be used together with your custom
views.
Moving forward, your Project Management methodology might
contain a method to manage risks and issues. This post is about configuring
your own Project Online instance to match your Risk and Issue Management
methodology. I choose the Issue list as an example but the same applies to
Risks or Documents. Note that identical approach can be used for any custom
features such as change requests, decisions log, assumptions and constraints…
Approach
The implementation relies on the usage of SharePoint Content
Types. You can find more information on this topic reading: Introduction to Content Types on MSDN. Content Types, being
centrally managed, can be easily updated to reflect your methodology changes,
and those changes can be applied to any existing Project Site (avoiding to ask
you poor dev team to manually update all project site lists after any changes).
The trick is to
update the existing Risk or Issue Content Types (or create your own),
understanding that Project Online relies on some fields of those content types.
It means that you should never delete
any of the existing fields. If you remove some fields (aka the trap of the beginner),
the publish process may throw an error. Even for SharePoint dev superheroes,
it’s very complex to recreate those fields (it’s not just a story of recreating
the fields with the same names). You cannot delete fields, but you can create
new ones or hide some of the existing.
If you are not familiar with this, here is a step by step procedure
to create your own Issue Content Type and use it in Project Online.
Managing risks and issues with Project Server 2013 (or Project Online)
As part of
your projects’ management, you will most probably have to manage risks and
issues.
The goal of
this article is to show how risks and issues (but also documents or
deliverables) can be managed within Project Server 2013 (or Project Online) and
linked with Projects, Tasks or any other assets.
Before we
start, let see how the Project Management Institute (PMI) defines issue and risk:
Issue: A point or matter in question or in dispute, or a point or matter that
is not settled and is under discussion or over which there are opposing views
or disagreements.
Risk: An uncertain event or condition that, if it occurs, has a positive or
negative effect on one or more project objectives.
Project Management Institute. (2013). A guide to the project management
body of knowledge (PMBOK® guide) – Fifth Edition.
In fewer
words, risks might occur and we need to manage this eventuality, where issues
are events that are already happening and we need to manage consequences.
My project
For the
demo, we will use a simple project called [Related
items project], that has the following schedule.New free webinars
From PM Center Usa, 2 news and FREE interesting webinars:
I would love to know the arguments of the speaker regarding Earned Value Management and the fact that this do not work... Will see...
- Risk Management Made Easy for Projects on Oct. 28, 2010 18:00(CET), Register here
- Earned Value Analysis – Why it Doesn’t Work on Nov. 4, 2010 17:00 (CET), Register here
I would love to know the arguments of the speaker regarding Earned Value Management and the fact that this do not work... Will see...
Subscribe to:
Posts
(
Atom
)