Updating the Status Manager, the sleight of hand
The status manager is
the resource who is to receive status updates for a task, from any resource
assigned to this task. The Status Manager (task field) is described in this page from Microsoft support.
Known limitation
Microsoft Project has
a limitation that prevents a schedule owner from setting a task’s status manager
to anyone except himself or herself. Hence, if you want to assign another
person as the Status Manager to a task within your project plan, you need to
ask him/her to edit the schedule in Microsoft Project and assign himself or herself
as the Status Manager.