Updating the Status Manager, the sleight of hand

3 comments
The status manager is the resource who is to receive status updates for a task, from any resource assigned to this task. The Status Manager (task field) is described in this page from Microsoft support.

Known limitation
Microsoft Project has a limitation that prevents a schedule owner from setting a task’s status manager to anyone except himself or herself. Hence, if you want to assign another person as the Status Manager to a task within your project plan, you need to ask him/her to edit the schedule in Microsoft Project and assign himself or herself as the Status Manager.